STAKEHOLDER PORTAL / PROJECT RED MESA
Project Red Mesa — Engineering
Hydra forward-deployed engineers · Dana K., FDE lead
01 / MY NEXT STEP
Draft acceptance test plan + thresholds for MSA
openDUE DEC 30
02 / WHAT WE NEED FROM YOU
2 open actions
T12Draft acceptance test plan + thresholds for MSA
T13Rack elevation + network design to colo
03 / WHAT CHANGED
Since your last visit
DECISION #3
Lead time 19 → 32 weeks; RFS moved to Jul 12–Aug 2, 2027
DECISION #4
Hall B rejected; Hall A required
ACTION PLAN
Your action plan
T12Draft acceptance test plan + thresholds for MSA
Hydra forward-deployed engineers · Gate D
T13Rack elevation + network design to colo
Hydra forward-deployed engineers · Gate C
SHARED DEAL STATE
Deal status
GATE ACommercialblocked
GATE BCapitalnot started
GATE CSite / colopassed
GATE DAcceptancenot started
CONTACTS
Your contacts
Your teamDana K., FDE lead
Hydra AI FactoryMatthew D., AI Factory lead
DELIVERY MILESTONES
Key dates
SHIP DATE · SUPERMICROFri Jun 4, 2027
READY-FOR-SERVICE · RANGEJul 12 – Aug 2, 2027
SHIP ≠ RFSShip Jun 4 → Dock Jun 14 → Rack & stack Jun 15–25 → Burn-in Jun 28–Jul 5 → Acceptance Jul 9 → RFS Jul 12–Aug 2.
DEPLOYMENT / TESTING
Install and acceptance
Rack & stack Jun 15–25PENDING
DCGM → HPL → NCCL (2 nodes → full)PENDING
24h real job; burn-in 3–7 daysPENDING
Acceptance certificate vs agreed MSA thresholdsPENDING
Brokkr out-of-band onboardingPENDING
SHARED REPOSITORY
Your documents
Hidden from this view: Commercial terms (price, fee, loan).