Mock deal for demo — all parties fictional. Figures are illustrative placeholders, not quotes.
PREVIEWING AS INVESTOR · This is what Meridian Ridge Capital seesBack to internal
STAKEHOLDER PORTAL / PROJECT RED MESA

Project Red Mesa — Investor

Meridian Ridge CapitalFICTIONAL · R. Okafor, Managing Partner

active
Get text updates when your next step changes

Stay current on decisions, dates, and actions shared with your team.

01 / MY NEXT STEP

Board sign-off on credit-support swap

openDUE DEC 21
02 / WHAT WE NEED FROM YOU

1 open actions

T5Board sign-off on credit-support swap
Dec 21
03 / WHAT CHANGED

Since your last visit

DECISION #5

Colo term = 3 years + 1 renewal (≥ offtake term)

DECISION #6

3-mo prepay + parent guarantee instead of 20% LC; +100 bps accepted (Quillfield pending)

GATE UPDATE

Gate C passed Nov 20.

ACTION PLAN

Your action plan

T4Approve +100 bps model impact (decision #6)
Meridian Ridge Capital · Gate A
Dec 16
T5Board sign-off on credit-support swap
Meridian Ridge Capital · Gate A
Dec 21
SHARED DEAL STATE

Deal status

GATE ACommercialblocked
GATE BCapitalnot started
GATE CSite / colopassed
GATE DAcceptancenot started
CONTACTS

Your contacts

Your teamR. Okafor, Managing Partner
Hydra AI FactoryMatthew D., AI Factory lead
DELIVERY MILESTONES

Key dates

SHIP DATE · SUPERMICROFri Jun 4, 2027
READY-FOR-SERVICE · RANGEJul 12 – Aug 2, 2027
SHIP ≠ RFS

Ship Jun 4 → Dock Jun 14 → Rack & stack Jun 15–25 → Burn-in Jun 28–Jul 5 → Acceptance Jul 9 → RFS Jul 12–Aug 2.

INVESTOR VIEW · ILLUSTRATIVE

Economics

ALL-IN CAPEX~$30M
CAPITAL STACK30 / 70~$9M equity · ~$21M delayed-draw loan
OFFTAKE$3.10per GPU-hour · 3-year take-or-pay
MOCK REVENUE~$15.6M/ year · ~$46.9M over term
SHARED REPOSITORY

Your documents

View all
Hidden from this view: Hydra negotiating notes, internal fee math beyond agreed terms, other investors considered.
SCHEDULE LOGIC

Worked back from RFS window

RFSJul 12–Aug 2
AcceptanceJul 9
Burn-inJun 28
RackJun 15
DockJun 14
ShipJun 4
POOct 23
Gate CNov 20
Latest safe dates Gate A · Jan 15 Gate B · Feb 12

Ship Jun 4 → Dock Jun 14 → Rack & stack Jun 15–25 → Burn-in Jun 28–Jul 5 → Acceptance Jul 9 → RFS Jul 12–Aug 2.