STAKEHOLDER PORTAL / PROJECT RED MESA

Project Red Mesa — Offtaker

Quillfield Inference Co.FICTIONAL · S. Patel, VP Infrastructure

active
Get text updates when your next step changes

Stay current on decisions, dates, and actions shared with your team.

01 / MY NEXT STEP

Respond to credit-support proposal (3-mo prepay + parent guarantee)

openDUE DEC 18
02 / WHAT WE NEED FROM YOU

3 open actions

T1Upload trailing-12-month financials for lender
Dec 18
T2Respond to credit-support proposal (3-mo prepay + parent guarantee)
Dec 18
T3Complete KYC/AML forms
Dec 22
03 / WHAT CHANGED

Since your last visit

DECISION #3

Lead time 19 → 32 weeks; RFS moved to Jul 12–Aug 2, 2027

DECISION #6

3-mo prepay + parent guarantee instead of 20% LC; +100 bps accepted (Quillfield pending)

DOCUMENT UPDATE

Term Sheet v2 adds a credit-support section.

ACTION PLAN

Your action plan

T1Upload trailing-12-month financials for lender
Quillfield Inference Co. · Gate B
Dec 18
T2Respond to credit-support proposal (3-mo prepay + parent guarantee)
Quillfield Inference Co. · Gate A
Dec 18
T3Complete KYC/AML forms
Quillfield Inference Co. · Gate B
Dec 22
SHARED DEAL STATE

Deal status

GATE ACommercialblocked
GATE BCapitalnot started
GATE CSite / colopassed
GATE DAcceptancenot started
CONTACTS

Your contacts

Your teamS. Patel, VP Infrastructure
Hydra AI FactoryMatthew D., AI Factory lead
DELIVERY MILESTONES

Key dates

SHIP DATE · SUPERMICROFri Jun 4, 2027
READY-FOR-SERVICE · RANGEJul 12 – Aug 2, 2027
SHIP ≠ RFS

Ship Jun 4 → Dock Jun 14 → Rack & stack Jun 15–25 → Burn-in Jun 28–Jul 5 → Acceptance Jul 9 → RFS Jul 12–Aug 2.

Why RFS is a range

RFS follows dock, installation, burn-in, and signed acceptance; shipping alone does not start service.

SHARED REPOSITORY

Your documents

View all
Hidden from this view: Capex, loan terms, investor IRR, Hydra fee, other bidders, colo pricing.
SCHEDULE LOGIC

Worked back from RFS window

RFSJul 12–Aug 2
AcceptanceJul 9
Burn-inJun 28
RackJun 15
DockJun 14
ShipJun 4
POOct 23
Gate CNov 20
Latest safe dates Gate A · Jan 15 Gate B · Feb 12

Ship Jun 4 → Dock Jun 14 → Rack & stack Jun 15–25 → Burn-in Jun 28–Jul 5 → Acceptance Jul 9 → RFS Jul 12–Aug 2.